What |
We are looking to carry out some repair work to the bed of Nottingham Stream. |
---|---|
Why |
Repairs to the stream bed to ensure water will flow efficiently during a rain event. |
Where |
Nottingham Stream between Patterson Terrace and Nicholls Road. |
When |
Work will start on 11 January 2021 and is expected to be completed by 22 January 2021 (weather dependent). |
Contact |
The contractor is City Care. Phone Melissa Cameron 027 307 3130. |
This work will include:
Noise
There may be increased noise, dust and vibrations during work but it shouldn’t impact on your power, water, gas or phone services.
Safety
Safety is our biggest priority so please keep children and pets away from worksites.
Bins