Date | Actions |
April 2013 Project set up |
Earthquake impacts assessed, technical information gathered and key stakeholders identified. |
June 2013 Research, information gathering |
Focus group sessions with key stakeholders and residents held. Community’s values, needs, aspirations and priorities identified. |
June 2013 Design & feasibility testing |
Technical expert workshop held to combine and reconcile community’s values, needs, aspirations and priorities. |
June-September 2013 Prepare draft master plan |
Discussions with stakeholders continued as master plan was drafted. Endorsed by Community Board. Approved by Council for public notification. |
October-November 2013 Consultation |
Public consultation held and 216 submissions received. |
March-November 2014 Follow up investigations, revisions |
Submissions analysed. Further investigations as needed. Submissions heard. Amendments to draft master plan. |
November 2014 Adoption |
Main Road Master Plan adopted by Council. |
December 2014 onwards Implementation |
Actions implemented by community and Council (capital projects delivered as funding made available). |