The Linwood Village Master Plan provides a way to create a lively urban village full of colour, life and energy, truly reflecting the character of the people who make this place their home.

Linwood vision

An artist's impression of a redeveloped Linwood Village looking west from the corner of Worcester Street and Stanmore Road.

Date Actions
July 2011
Project set up 
Earthquake impacts assessed, scope confirmed and key stakeholders identified.
August 2011
Research, information gathering 
Focus group sessions with key stakeholders and residents held. Key issues and opportunities identified.
September 2011
Design and feasibility testing
Technical expert workshops held. Best ways to address issues and suggestions from the community identified via a community feedback presentation.
September–December 2011
Prepare draft master plan 
Master plan drafted. Endorsed by Community Board. Approved by Council for public notification.
December 2011
Consultation 
Public consultation held and 36 submissions received.
January–May 2012 
Follow up investigations, revisions 
Submissions analysed. Further investigations as needed. Community Board recommendation to hold a submitters’ workshop instead of formally hearing submissions endorsed by Council. Amendments to draft master plan.
August 2012
Adoption
Linwood Village Master Plan adopted by Council.
September 2012 onwards
Implementation 
Actions implemented by community and Council (capital projects delivered as funding made available).

The Linwood Village Master Plan contains a strategic vision to transform the centre into a lively, colourful, diverse and eclectic urban village.

The vision is supported by five goals, which are to be delivered through eight detailed implementation actions/projects.

These encourage Council, private sector, community and government-led decision making to align and move forward together in a logical sequence.

The associated vision, goals and actions are described in detail on pages 11, 12 and 25 of the Linwood Village Master Plan [PDF, 4.8 MB].

Key successes to date include:

  • Doris Lusk Park has been upgraded, including a new toilet block, drinking water fountain, bike fix-it and landscaping.
  • The Green Lab (formally Greening the Rubble) has worked with the Council and the Linwood community to implement a transitional project, the ‘Linwood Tiny Shops’, on a vacant commercial site, to provide another community hub and focal point, including small-scale commercial spaces, a community garden and play space.
  • The Major Cycle Route, Rapanui – Shag Rock section through Linwood Village, including improvement works to the intersection of Stanmore Road and Worcester Street, have been completed.
  • External lighting of the Linwood Community Arts Centre, to highlight the heritage features of the building, has been completed.

To view the corresponding master plan actions, go to page 25 in the Linwood Village Master Plan [PDF, 4.8 MB].

  • Following early engagement, preparation has commenced on the design of the ‘Linwood Village streetscape upgrade’ (S1). The project is funded in the current Annual Plan and will be delivered over the next two years.
  • The preferred design for the ‘Doris Lusk Park children’s interactive play/art project’ (C1) is undergoing feasibility work, with installation deferred to 2022 due to the Covid lockdown.

To view the corresponding master plan actions, go to page 25 in the Linwood Village Master Plan [PDF, 4.8 MB].