Date | Actions |
August 2011 Project set up |
Earthquake impacts assessed, technical information gathered and key stakeholders identified. |
October 2011 Research, information gathering |
Focus group sessions with key stakeholders and residents held. Community’s values, needs, aspirations and priorities identified. |
November 2011 Design & feasibility testing |
Technical expert workshops held to combine and reconcile community’s values, needs, aspirations and priorities. |
December 2011-November 2012 Prepare draft master plan |
Master plan drafted. Endorsed by Community Board. Approved by Council for public notification. |
January-February 2013 Consultation |
Public consultation held and submissions received. |
May-June 2013 Follow up investigations, revisions |
Submissions analysed. Further investigations as needed and focus group sessions and community workshops held. Amendments to draft master plan. |
May 2014 Adoption |
Ferry Road Master Plan adopted by Council. |
June 2014 onwards Implementation |
Actions implemented by community and Council (capital projects delivered as funding made available). |