Date | Actions |
April 2012 Project set up |
Earthquake impacts assessed, scope confirmed and key stakeholders identified. |
June 2012 Research, information gathering |
Focus group sessions with key stakeholders and residents held. Key issues and opportunities identified. |
July 2012 Design & feasibility testing |
Technical expert workshops held. Best ways to address issues and suggestions from the community identified. |
August 2012-February 2013 Prepare draft master plan |
Master plan drafted. Endorsed by Community Board. Approved by Council for public notification. |
March-April 2013 Consultation |
Public consultation held and 75 submissions received. |
May-December 2013 Follow up investigations, revisions |
Submissions analysed. Further investigations as needed. Community Board recommendation not to hear submissions endorsed by Council. Amendments to draft master plan. |
December 2013 Adoption |
Edgeware Village Master Plan adopted by Council. |
July 2012 onwards Implementation |
Actions implemented by community and Council (capital projects delivered as funding made available). |